Case Study

Morphett vale

Description
Major internal renovation in two stages
Duration
Stage 1. – 5 weeks   Stage 2. – 3 weeks
Project Value
$88,000
The clients, a couple with teenaged kids needed more space in their 40 year old home as well as new toilet, bathroom, an upgraded laundry and a new larger on suite.
In order to create an open plan kitchen and dining area, the loadbearing brick walls needed to be removed and replaced with engineered structural steel beams and columns.
The enlarging on-suite be 5 square meters required taking down and rebuilding walls adjacent to it as well as strengthening the roof structure.

Other aspects of the job included:

Complete renovation of bathroom, toilet, laundry and on suite including taps, shower screens, vanities, toilet pans, bath tub, benches, hooks, rails etc.

Relocating toilet pan and bath tub

Replacing ceilings in all wet areas and corridors

Removing loadbearing brick walls and replacing it with structural steel beams and columns

Reinforcing roof structure

Building bulkheads, shifting walls to increase room sizes

Fix, sand and polish wooden floors

New doors with handles and architraves

Cavity slider and sliding barn door

New skirting board and cornice

New LED down lights throughout. Extra light switches and power points.

Other relevant electrical works

New paint to all walls and ceilings in worked areas

40sq/m of new laminated flooring

Ensuite

Bathroom

Laundry Renovation

Before
During
During
After

Main Area